SOLUTION: A building contractor agrees to pay a fine for all the days he is late completing a job. The penalty for being one day late is set at $45. Each day after that, the penalty is inc

Algebra ->  Customizable Word Problem Solvers  -> Finance -> SOLUTION: A building contractor agrees to pay a fine for all the days he is late completing a job. The penalty for being one day late is set at $45. Each day after that, the penalty is inc      Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 250149: A building contractor agrees to pay a fine for all the days he is late completing a job. The penalty for being one day late is set at $45. Each day after that, the penalty is increased by $10, and it is cumulative! If the contractor's penalty turns out to be $1725, how many days late is he in completing the job?
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
if it costs $45the first day and each subsequent day costs $10
dayone =45
others=10d
dayone + others=1725
we have 45+10d=1725
solve for d and add one for the first day
The contractor was very late.