SOLUTION: It takes 18 men 6 hours to dig a trench 720 feet long. Working at the same rate, how many feet of trench can be dug by 24 men in 8 hours?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: It takes 18 men 6 hours to dig a trench 720 feet long. Working at the same rate, how many feet of trench can be dug by 24 men in 8 hours?
Log On
You can put this solution on YOUR website! It takes 18 men 6 hours to dig a trench 720 feet long.
Working at the same rate, how many feet of trench can be dug by 24 men in 8 hours?
:
We can use man-hrs here.
:
18*6 = 108 man-hrs for 720 ft
that's = 6 ft per man-hr
:
24 * 8 * 6 = 1280 ft