SOLUTION: It takes 5 boys or 8 girls complete a job in 26 days. How many days would it take 4 boys and 5 girls to complete the same job?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: It takes 5 boys or 8 girls complete a job in 26 days. How many days would it take 4 boys and 5 girls to complete the same job?
Log On
Question 221771: It takes 5 boys or 8 girls complete a job in 26 days. How many days would it take 4 boys and 5 girls to complete the same job? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! This problem is about the rates at which
boys and girls do a certain "job".
given:
The rate for 5 boys is 1 job/26 days.
Each boy can do 1/5 of a job in 26 days because
How long does it take a boy to do 1 job?
1 boy can do 1 job in 130 days
likewise,
The rate for 8 girls is 1 job/26 days
Each girl can do 1/8 job in 26 days
How long does it take a girl to do 1 job?
A girl can do 1 job in 208 days
I can add up the rates for 4 boys and 5 girls
to get their rate working together
Let = number of days for 4 boys and 5 girls
to complete job
Multiply both sides by days
check answer
OK
check for 5 boys
check for 8 girls
OK