SOLUTION: If 6 men can do a piece of work in 14 days, how many men are needed to do work in 21 days?
Algebra
->
Customizable Word Problem Solvers
->
Misc
-> SOLUTION: If 6 men can do a piece of work in 14 days, how many men are needed to do work in 21 days?
Log On
Ad:
Over 600 Algebra Word Problems at edhelper.com
Word Problems: Miscellaneous Word Problems
Word
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Miscellaneous Word Problems
Question 204106
:
If 6 men can do a piece of work in 14 days, how many men are needed to do work in 21 days?
Found 2 solutions by
scott8148, RAY100
:
Answer by
scott8148(6628)
(
Show Source
):
You can
put this solution on YOUR website!
it takes 84 man-days (6 * 14) to do the job
to do the job in 21 days would take 4 men (84 / 21)
Answer by
RAY100(1637)
(
Show Source
):
You can
put this solution on YOUR website!
1 job= 6 men *14 days = 84 man-days = xmen * 21 days,,,,,x=84/21= 4 men