| Question 171184:  One person can do a job in 8 hours. A second person can do it in 12 hours. If the first person works 2 hours less than the second, how many hours will it take them working together?
 Answer by ptaylor(2198)
      (Show Source): 
You can put this solution on YOUR website! Let t=time it takes them working together First person works at the rate of 1/8 job per hour
 Second person works at the rate of 1/12 job per hour
 Together they work at the rate of 1/8 + 1/12 =3/24 + 2/24 =5/24 job per hour
 While the first person is not working for 2 hours, the second person will complete(1/12)*2=1/6 of the job, leaving 5/6 of the job yet to do. So, they both will work together to complete the remaining 5/6 of the job
 So, our equation to solve is:
 (5/24)*t=5/6  multiply each side by 24
 5t=20
 t=4 hours-------------time it takes them working together to finish the job.
 CK
 (1/12)*2+(5/24)*4=1 (1 job, that is)
 1/6 +20/24=1
 4/24 + 20/24=1
 1=1
 Hope this helps---ptaylor
 
 | 
  
 | 
 |  |  |