Question 150999:  Mike, Joe, and Bill are painting a fence. The painting can be finished if Mike and Joe each work for 4 hours and Bill works for 2 hours; or if Mike and Joe each work for 2 hours and Bill works for 5 hours; or if Mike works for 6 hours, Joe works for 2 hours, and Bill works for 1 hour. How much time does it take for each man working alone to complete the painting? 
 Answer by ptaylor(2198)      (Show Source): 
You can  put this solution on YOUR website! Let x=Mike's rate of work (in fences (or fractions thereof) painted per hour) 
Let y=Joe's rate of work 
Let z=Bill's rate of work
 
Now we know the following:
 
Mikes rate of work times the number of hours worked Plus Joe's rate of work times the number of hours worked plus Bill's rate of work times the number of hours worked equals 1 fence painted, so our equations to solve are:
 
4x+4y+2z=1--------------------------eq1 
2x+2y+5z=1----------------------------eq2 
6x+2y+z=1---------------------------eq3
 
Multiply eq2 by 2 and subtract it form eq1 
4x+4y+2z=1---eq1 
4x+4y+10z=2---eq2a 
and we get: 
-8z=-1 
z=1/8----Bill's rate of work is 1/8 fence per hour so it follows that in 8 hours he can paint the fence alone 
Next, subtract eq2 from eq3 
6x+2y+z=1----------------eq3 
2x+2y+5z=1--------------eq2 
And we get:
 
4x-4z=0 or 
x=z=1/8-------------Mike's rate of work is also 1/8 fence per hour so in 8 hours Mike can also paint the fence alone
 
Now we substitute x=1/8 and z=1/8 into eq1
 
4*(1/8)+4y+2*(1/8)=1 simplify 
1/2+4y+1/4=1 further simplify 
4y + 3/4 =1  subtract 3/4 from each side 
4y=1/4  divide each side by 4 
y=1/16-------------------Joe's rate of work is 1/16 fence per hour so in 16 hours Joe can paint the fence alone
 
CK 
4*(1/8)+4*(1/16)+2*(1/8)=1 
1/2+1/4+ 1/4=1 
1=1 
same should work for the other two equations
 
Hope this helps----ptaylor
 
 
  | 
 
  
 
 |   
 
 |   
 |  |