Question 131386: I have a homework problem that I can't seem to solve. Could someone help me please. thank you. Sam accepted a job to brick a new home. He calculated that he can complete the job in 4 hours. He hired a trainee to assist him. He has seen the trainee work. He estimates that the trainee working alone would take 6 days to complete the job. How much time should the two of them working together need to brick the house?
Answer by stanbon(75887) About Me  (Show Source):
You can put this solution on YOUR website!
Sam accepted a job to brick a new home. He calculated that he can complete the job in 4 hours. He hired a trainee to assist him. He has seen the trainee work. He estimates that the trainee working alone would take 6 days to complete the job. How much time should the two of them working together need to brick the house?
---------------
Sam DATA:
Time = 4 HOURS/job ; Rate = 1/4 job/hr
--------------
Assist DATA:
Time = 6 DAYS
-----------------
Comment: Are you sure your mean 4 Hours for one and 6 days for the other?
Cheers,
Stan H.