SOLUTION: 116.6% of the work done by B at 10% of his efficiency is equal to  25% of the work done by A when he work at 75% more than his  efficiency. Both A and B working together can

Algebra ->  Customizable Word Problem Solvers  -> Travel -> SOLUTION: 116.6% of the work done by B at 10% of his efficiency is equal to  25% of the work done by A when he work at 75% more than his  efficiency. Both A and B working together can      Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 1201576: 116.6% of the work done by B at 10% of his efficiency is equal to 
25% of the work done by A when he work at 75% more than his 
efficiency. Both A and B working together can complete the work in 6 
days. Find the time taken by B to complete the whole work ?

Found 2 solutions by Edwin McCravy, ikleyn:
Answer by Edwin McCravy(20065) About Me  (Show Source):
You can put this solution on YOUR website!
Suppose A can do 1 job in x days at 100% efficiency, so his work rate is 1/x
jobs per day.

B can do 1 job in y days at 100% efficiency, so his work rate is 1/y jobs per
day

>>>Both A and B working together [at 100% efficiency] can complete the work in
6 days.<<<

6%2Fx+%2B+6%2Fy+=+1

At 10% [1%2F10] 1efficiency, B's work rate is 1%2F%2810y%29 jobs per day.

At 75% [3%2F4] more than his efficiency, A's work rate is 175% [1%263%2F4
or 7%2F4]
 or 7%2F%284x%29 jobs per day.



>>>116.6% of the work done by B at 10% of his efficiency<<<

That means in any given amount of time, say 1 unit of time, so it says

116.6% of the work done by B at 10% of his efficiency in 1 unit of time:

[I'm going to consider that as 116.6666666...% or %221.166666666...%22+=+1%261%2F6
or 7%2F6, to avoid god-awful decimals or fractions.]

That's %287%2F6%29%281%2F%2810y%29%2A1%29, or 7%2F%2860y%29

>>>is equal to<<< 

>>>25% [1/4] of the work done by A when he works at 75% more than his 
efficiency.<<<

That means in the same amount of time, say 1 unit of time, so it says

So 1%2F4 of A's work rate at 1%263%2F4%22%22%2A%22%221

That's %281%2F4%29%287%2F%284x%29%29+=+7%2F%2816x%29 jobs per day.

So we have the equation

7%2F%2860y%29+=+7%2F%2816x%29

7%2816x%29=7%2860y%29

16x=60y

4x=15y

x=15y%2F4

Substitute in

6%2Fx+%2B+6%2Fy+=+1

6%5E%22%22%2F%2815y%2F4%29+%2B+6%2Fy+=+1

Multiply the first term by 4%2F4

24%2F%2815y%29+%2B+6%2Fy+=+1
8%2F%285y%29+%2B+6%2Fy+=+1
expr%281%2Fy%29%288%2F5%2B6%29=1
expr%281%2Fy%29%2838%2F5%29=1
Multiply through by 5/38
1%2Fy=5%2F38
Take reciprocals
y=38%2F5
y=7.6  <--- Answer: B can do 1 job in 7.6 days.

Edwin

Answer by ikleyn(52915) About Me  (Show Source):
You can put this solution on YOUR website!
.
116.6% of the work done by B at 10% of his efficiency is equal to
25% of the work done by A when he work at 75% more than his
efficiency. Both A and B working together can complete the work in 6
days. Find the time taken by B to complete the whole work ?
~~~~~~~~~~~~~~~~~~


            This problem is on a  "rate of work ".


Let x be the A's rate of work; 

Let y be the B's rate of work.


The first statement "116.6% of the work done by B at 10% of his efficiency is equal to 
                     25% of the work done by A when he work at 75% more than his efficiency"
means that

    1.166*(0.1y) = 0.25*(1+0.75)x.


Also, understanding that the problem's creator wanted to say " 116.6...% " instead of 116.6% 
(kind of joke from his side), we can rewrite this equation in the form
 ~~~~~~~~~~~~~~~~~~~~~~~~~~

    11%2F6*%281%2F10%29%2Ay = %281%2F4%29%2A%287%2F4%29x,

or

    %287%2F6%29%2A%281%2F10%29y = %281%2F4%29%2A%287%2F4%29x.


Reducing the factor 7 in both sides, we get

    y%2F60 = x%2F16,  or  y%2F15 = x%2F4,  or  x = %284%2F15%29%2Ay.    (1)



The second statement "Both A and B working together can complete the work in 6 days"                     
means that

    x + y = 1%2F6.



Substitute here  x = %284%2F15%29%2Ay  from (1),  and you will get

    %284%2F15%29y + y = 1%2F6,

or

    %2819%2F15%29y = 1%2F6,  y = %28%281%2F6%29%29%2F%28%2819%2F15%29%29 = 15%2F%286%2A19%29 = 5%2F%282%2A19%29 = 5%2F38.


It means that B can complete the job in  38%2F5 = 73%2F5  days working alone.    ANSWER

Solved.


/////////////////


So,  this problem is partly  " a joke ",  but it is a bit a crocked/curved joke.

Me,  from my side,  tried to teach you on how to solve this problem and similar problems in a rational way.

"A rational way" in this case means "saying minimum words and writing minimum equations,
                                     but still enough in order for everything be clear".