Question 1200680: When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 26 days by 23 workers. How many days would it take to build a similar house with 46 workers?
Answer by Alan3354(69443) About Me  (Show Source):
You can put this solution on YOUR website!
When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 26 days by 23 workers. How many days would it take to build a similar house with 46 workers?
---------------
Twice the # of workers ---> 1/2 the time.