|  | 
| 
 
 
| Question 1197748:  When A,B and C work together, they can finish
 installing the garden in 3 days. The job could be
 completed of A worked 4 days alone and
 C worked 10 days alone or if B worked 5 days alone and C worked 3 days alone. How many days would it take  each worker alone to complete the garden?
 Answer by ikleyn(52879)
      (Show Source): 
You can put this solution on YOUR website! . When A,B and C work together, they can finish installing the garden in 3 days.
 The job could be completed of A worked 4 days alone and C worked 10 days alone
 or if B worked 5 days alone and C worked 3 days alone.
 How many days would it take each worker alone to complete the garden?
 ~~~~~~~~~~~~~~~~~~~
 
 
 
Let  "a"  be the A's rate of work, in job per day;
     "b"  be the B's rate of work, in job per day;
     "c"  be the C's rate of work, in job per day.
From the condition, we have this system of 3 equations in 3 unknowns
    a + b + c =  ,           (1)
    4a + 10c = 1,             (2)
    5b +  3c = 1.             (3)
To solve, express  a =  from (2), and express  b =  from (3).
Substitute these expressions into equation (1).  You will exclude "b" and "c" from (1)
and will get single equation for unknown "c"  +  + c =  .      (4)
Multiply both sides by 60
    15(1-10c) + 12*(1-3c) + 60c = 20
    15 - 150c + 12 - 36c + 60c = 20
    27 - 126c = 20
    27 - 20 = 126c
       7    = 126c
       c    =  =  .
It means that C will complete the job in 18 days working alone.
Now   a =  =  =  =  ;
      b =  =  =  =  .
ANSWER.  A can complete the job in 9 days working alone;
         B can complete the job in 6 days working alone;
         C can complete the job in 18 days working alone.Solved.
 
 
 
 | 
  
 | 
 |  |  |