Question 1195920
:
If 12 men can dig a trench in 8 days how many men can dig it in 6 days
Found 2 solutions by
josgarithmetic, greenestamps
:
Answer by
josgarithmetic(39617)
(
Show Source
):
You can
put this solution on YOUR website!
, r for one-man rate, but is really not needed; y number of men (for 6 days).
Answer by
greenestamps(13200)
(
Show Source
):
You can
put this solution on YOUR website!
The other tutor shows one of many formal ways for solving problems like this; different students will prefer different methods.
I find a more informal method much easier:
3/4 as many days means 4/3 as many men.
ANSWER: 12*(4/3) = 16 days