SOLUTION: IT TAKES 20 MEN 60DAYS TO COMPLETE A BUILDING WORK, HOW MANY DAYS LONGER WOULD IT TAKES 15 MEN ASSURING THAT THEY ALL WORK AT THE SAME RATE
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: IT TAKES 20 MEN 60DAYS TO COMPLETE A BUILDING WORK, HOW MANY DAYS LONGER WOULD IT TAKES 15 MEN ASSURING THAT THEY ALL WORK AT THE SAME RATE
Log On
Question 1191584: IT TAKES 20 MEN 60DAYS TO COMPLETE A BUILDING WORK, HOW MANY DAYS LONGER WOULD IT TAKES 15 MEN ASSURING THAT THEY ALL WORK AT THE SAME RATE Found 4 solutions by josgarithmetic, Alan3354, greenestamps, MathTherapy:Answer by josgarithmetic(39630) (Show Source):
You can put this solution on YOUR website! IT TAKES 20 MEN 60DAYS TO COMPLETE A BUILDING WORK, HOW MANY DAYS LONGER WOULD IT TAKES 15 MEN ASSURING THAT THEY ALL WORK AT THE SAME RATE
----------------
Jobs are often expressed in man-hours of man-days estimated to do them.
20*60 = 1200 man-days
1200/15 = 80 days
You can put this solution on YOUR website!
IT TAKES 20 MEN 60DAYS TO COMPLETE A BUILDING WORK, HOW MANY DAYS LONGER WOULD IT TAKES 15 MEN ASSURING THAT THEY ALL WORK AT THE SAME RATE
Time it takes 15 men, working at the same rate, or
Days longer that it'd take 15 men: 80 - 60 = 20