If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole at the same rate?
Answer by
ikleyn(52775)
(
Show Source
):
You can
put this solution on YOUR website!
.
The whole job is 6*10 = 60 man-days.
12 men will complete it in
= 5 days.
ANSWER
Solved.