SOLUTION: If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole at the same rate?

Algebra ->  Average -> SOLUTION: If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole at the same rate?      Log On


   



Question 1189492: If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole at the same rate?
Answer by ikleyn(52776) About Me  (Show Source):
You can put this solution on YOUR website!
.

The whole job is   6*10 = 60 man-days.

12 men will complete it in   60%2F12 = 5 days.             ANSWER