SOLUTION: 4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the same job in 6 days. How long does it take 1 skilled work and 1 semi-skilled worker to comple
Algebra ->
Customizable Word Problem Solvers
-> Mixtures
-> SOLUTION: 4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the same job in 6 days. How long does it take 1 skilled work and 1 semi-skilled worker to comple
Log On
Question 1185686: 4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the same job in 6 days. How long does it take 1 skilled work and 1 semi-skilled worker to complete the same job if they work together?
You can put this solution on YOUR website! .
4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the same job in 6 days.
How long does it take 1 skilled work and 1 semi-skilled worker to complete the same job if they work together?
~~~~~~~~~~~~~~~~
Rate of work of one skilled worker is = of the job per day.
Rate of work of one semi-skilled worker is = of the job per day.
When one skilled worker and one semi-skilled worker work together, their combined rate of work is
+ = + = = of the job per day.
It means that one skilled worker and one semi-skilled worker will complete the job in 12 days working together. ANSWER