Question 1185686: 4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the same job in 6 days. How long does it take 1 skilled work and 1 semi-skilled worker to complete the same job if they work together?
Found 2 solutions by josgarithmetic, ikleyn: Answer by josgarithmetic(39838) (Show Source): Answer by ikleyn(53937) (Show Source):
| |
|