SOLUTION: A construction project is at present 30 days away from the scheduled completion date. Depending on the weather condition next month ,the time required for the remaining constructio

Algebra ->  Probability-and-statistics -> SOLUTION: A construction project is at present 30 days away from the scheduled completion date. Depending on the weather condition next month ,the time required for the remaining constructio      Log On


   



Question 1169639: A construction project is at present 30 days away from the scheduled completion date. Depending on the weather condition next month ,the time required for the remaining construction are as follows :
If weather is good, the time required distribution would be: normal, mean=25 ,Standard deviation = 4
If weather is Bad, the time required distribution would be: Log-Normal mean=30,Standard deviation =6
The weather next month would be equally likely to be either good or bad. What is the probability that there will be a delay in the completion of the project

Answer by CPhill(1959) About Me  (Show Source):
You can put this solution on YOUR website!
Let's break down this problem step by step.
**Understanding the Problem**
We need to calculate the probability that the construction project will be delayed beyond the scheduled completion date, given two possible weather scenarios and their associated time requirements.
**Given Information**
* Current time until scheduled completion: 30 days
* Weather scenarios:
* Good weather: Normal distribution, mean (μ) = 25 days, standard deviation (σ) = 4 days
* Bad weather: Log-normal distribution, mean (μ) = 30 days, standard deviation (σ) = 6 days
* Weather likelihood: Equally likely (50% good, 50% bad)
**Solution**
1. **Good Weather Scenario:**
* We want to find the probability that the time required is greater than 30 days (delay).
* Since the distribution is normal, we need to calculate the z-score:
* z = (x - μ) / σ = (30 - 25) / 4 = 5 / 4 = 1.25
* We need to find P(Z > 1.25) using a standard normal distribution table or calculator.
* P(Z > 1.25) = 1 - P(Z ≤ 1.25) ≈ 1 - 0.8944 = 0.1056
2. **Bad Weather Scenario:**
* We want to find the probability that the time required is greater than 30 days.
* Since the distribution is log-normal, we need to convert the mean and standard deviation to the parameters of the underlying normal distribution.
* Let Y = ln(X), where X follows a log-normal distribution.
* E(X) = 30, SD(X) = 6.
* Var(X) = 36
* We use the following formulas to find the mean (μy) and standard deviation (σy) of Y:
* σy^2 = ln(1 + (Var(X) / E(X)^2)) = ln(1 + 36 / 900) = ln(1 + 0.04) = ln(1.04) ≈ 0.03922
* σy = √0.03922 ≈ 0.198
* μy = ln(E(X)) - 0.5 * σy^2 = ln(30) - 0.5 * 0.03922 ≈ 3.4012 - 0.01961 ≈ 3.3816
* Now, we need to find P(X > 30), which is equivalent to P(ln(X) > ln(30)) = P(Y > ln(30)).
* ln(30) ≈ 3.4012
* We calculate the z-score:
* z = (ln(30) - μy) / σy = (3.4012 - 3.3816) / 0.198 ≈ 0.0196 / 0.198 ≈ 0.09899
* We need to find P(Z > 0.099) using a standard normal distribution table or calculator.
* P(Z > 0.099) = 1 - P(Z ≤ 0.099) ≈ 1 - 0.5393 = 0.4607
3. **Combined Probability:**
* Since the weather is equally likely, we average the probabilities of delay for each scenario:
* P(delay) = (0.5 * 0.1056) + (0.5 * 0.4607) = 0.0528 + 0.23035 = 0.28315
**Final Answer**
The probability that there will be a delay in the completion of the project is approximately 0.2832.