SOLUTION: If A and B work on a project, they need 8 1/9 days. A worked alone for 8 days then B worked alone for 10 days and finished the project. In how many days can A complete the project

Algebra ->  Customizable Word Problem Solvers  -> Misc -> SOLUTION: If A and B work on a project, they need 8 1/9 days. A worked alone for 8 days then B worked alone for 10 days and finished the project. In how many days can A complete the project       Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 1163797: If A and B work on a project, they need 8 1/9 days. A worked alone for 8 days then B worked alone for 10 days and finished the project. In how many days can A complete the project alone? B?
Found 2 solutions by josgarithmetic, ikleyn:
Answer by josgarithmetic(39620) About Me  (Show Source):
You can put this solution on YOUR website!
system%281%2Fa%2B1%2Fb=1%2F%288%261%2F9%29%2C8%2Fa%2B10%2Fb=1%29

system%281%2Fa%2B1%2Fb=9%2F73%2C8%2Fa%2B10%2Fb=1%29

Maybe try A=1%2Fa and B=1%2Fb:

system%28A%2BB=9%2F73%2C8A%2B10B=1%29------------Maybe try elimination method from here.

Answer by ikleyn(52803) About Me  (Show Source):
You can put this solution on YOUR website!
.
If A and B work on a project, they need 8 1/9 days. A worked alone for 8 days then B worked alone for 10 days
and finished the project. In how many days can A complete the project alone? B?
~~~~~~~~~~~~~


Let "a" be the rate of work of A, i.e. the part of work which A makes per day.

Let "b" be the rate of work of B, i.e. the part of work which B makes per day.


First statement of the problem says that the combined rate of work of A and B, working together,

is the value reciprocal to  81%2F9 = 73%2F9

    a + b = 9%2F73.            (1)


The second statement of the problem says that

    8a + 10b = 1.           (2)



    Thus the setup is completed, and you have now two equations for two unknowns "a"  and  "b".



To solve this system of equations, multiply equation (1) by 8 (both sides).  Keep equation (2) as is.
You will get then

    8a +  8b = 72%2F73          (3)

    8a + 10b = 1             (4)


Next, subtract equation (3) from equation (4) (both sides).   You will get

          10b - 2b = 1 - 72%2F73,   or

           2b      = 73%2F73+-+72%2F73 = 1%2F73.


Hence,  b = 1%2F%282%2A73%29 = 1%2F146.

It means that B makes  1%2F146  of the job per day;  hence, B needs 146 days to complete the job alone.


Part of the problem is thus solved, and we need to find "a" now.


For it, from equation (2) you have

    8a = 1 - 10b = 1 - 10%2F146 = 136%2F146;

hence,  a = 136%2F146 : 8 = 17%2F146.


It means that A needs  146%2F17 = 8 10%2F17  days to complete the job alone.

Solved.

The numbers in the answer are ugly  (at least one is ugly),  but I checked them against the equations  (1)  and  (2),
and the answer is  CORRECT.