Question 1154714:  Howard and Edward, working together, can complete a job in 12 hours.  Edward requires 18 hours to do this job alone.  Howard and Edward start the job.  After they worked for 4 hours, Howard left the job.  How many hours will Edward require to finish the job working alone? 
 Found 3 solutions by  mananth, greenestamps, MathTherapy: Answer by mananth(16946)      (Show Source): 
You can  put this solution on YOUR website!  
Howard and Edward, working together, can complete a job in 12 hours.  Edward requires 18 hours to do this job alone.  Howard and Edward start the job.  After they worked for 4 hours, Howard left the job.  How many hours will Edward require to finish the job working alone?
 
Edward requires 18 hours to do this job alone.
 
He does 1/18 of job in 1 hour
 
Howard and Edward start the job they worked for 4 hours,
 
They can complete the job in 12 hours
 
So they can do 1/12 of the job in 1 hour 
they worked for 4 hours 
so they completed 4/12 of the job = 1/3 of the job
 
balance job = 1-1/3 = 2/3 of the job
 
Edward does 1/18 of job in 1 hour
 
for 1/3 of the job he will take (1/3)/(1/18) hours
 
(1/3) *18
 
6 hours
 
Edward will take 6 hours to complete the job
 
 
 
 
 Answer by greenestamps(13215)      (Show Source): 
You can  put this solution on YOUR website! 
  
They take 12 hours to do the job together.
  
In the beginning, they work together for 4 hours.  The fraction of the job that gets done is 4/12 = 1/3; 2/3 of the job remains.
  
Edward takes 18 hours to do the job alone.  To do the 2/3 of the job that remains alone, the required amount of time is 2/3 of 18 hours, or 12 hours.
  
 
 Answer by MathTherapy(10557)      (Show Source): 
You can  put this solution on YOUR website! Howard and Edward, working together, can complete a job in 12 hours.  Edward requires 18 hours to do this job alone.  Howard and Edward start the job.  After they worked for 4 hours, Howard left the job.  How many hours will Edward require to finish the job working alone? 
6 hours is WRONG!! 
If both can do the job in 12 hours, then in 4 hours, they will have done:   
With   of work completed by both, in 4 hours,   
With Edward taking 18 hours to do entire job alone, and doing   of job in 1 hour, time (T) taken by Edward to complete remaining   of job is:   
T, or time taken by Edward to complete remaining   of job =    
  | 
 
  
 
 |   
 
 |   
 |  |