Question 1148629: Hi
bob takes 4 hours to clean a room. Alan takes 2 hours. If bob started at 3pm and alan at 4pm what time did they finish.
thanks Found 3 solutions by greenestamps, josgarithmetic, ikleyn:Answer by greenestamps(13200) (Show Source):
Their combined rate of work is + = of the job per hour.
After Bob worked 1 hour alone, he completed of the job; hence, of the job remained.
With the combined rate of work of jobs per hour, the two workers will complete the whole job in 1 hour.
One hour after 4 pm is 5 pm. ANSWER