SOLUTION: A block industry estimates that 10 men must work for 8 hours each day to complete a job in 30 days. If only 8 men are to complete the job in 40 days, how long must they work each d
Algebra ->
Test
-> SOLUTION: A block industry estimates that 10 men must work for 8 hours each day to complete a job in 30 days. If only 8 men are to complete the job in 40 days, how long must they work each d
Log On
Question 1146122: A block industry estimates that 10 men must work for 8 hours each day to complete a job in 30 days. If only 8 men are to complete the job in 40 days, how long must they work each day? Answer by ankor@dixie-net.com(22740) (Show Source):
You can put this solution on YOUR website! A block industry estimates that 10 men must work for 8 hours each day to complete a job in 30 days.
If only 8 men are to complete the job in 40 days, how long must they work each day?
:
Find the number of man-hours required to do the job
10 * 8 * 30 = 2400 man-hours
:
let h = no. of hrs worked each day
8 * 40 * h = 2400
320h = 2400
h = 2400/320
h = 7.5 hrs a day