Question 1121257: The government is evaluating alternative routes for a new road into a formerly inaccessible region. Two routes are available and their pertinent data are tabulated below. The roads are assumed to have an economic life of 50 years, and interest rate- is 8%. By using B/C, which route should be selected?
Route A Route B
Construction Cost 1,850,000.00 2,200,000.00
Annual maintenance 20,000.00 30,000.00
Annual Savings in Flood Damage 50,000.00 70,000.00
Answer by solver91311(24713) (Show Source):
|
|
|