SOLUTION: a bricklayer can build a brick wall in 2 days. His apprentice needs 3 days to build the same wall. How long would it take them to build the wall if they work together?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: a bricklayer can build a brick wall in 2 days. His apprentice needs 3 days to build the same wall. How long would it take them to build the wall if they work together?
Log On
Question 1117456: a bricklayer can build a brick wall in 2 days. His apprentice needs 3 days to build the same wall. How long would it take them to build the wall if they work together? Answer by ikleyn(52781) (Show Source):
The master makes of the job per day.
The apprentice makes of the job per day.
Working together, they make = = of the job per day.
Hence, it will take them of the day = of the day to complete the job working together.
Solved.
---------------
It is a typical and standard joint work problem.