Question 1110376: 4 skilled workers can do a job in 5 days, 5 semi-skilled workers can do the same job in 6 days. How long does it take 1 semi-skilled and 2 skilled workers to do the job working together?
I think you do 5/4 and 5/6, and then you add 5/6+5/6+5/4. I'm not sure though.
Answer by josgarithmetic(39838) (Show Source):
| |
|
| |