SOLUTION: Mark can finish a task alone in 24 days while Andres can do the same task in 18 days. If they work together, how long can they finish the task?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: Mark can finish a task alone in 24 days while Andres can do the same task in 18 days. If they work together, how long can they finish the task?
Log On
Question 1093328: Mark can finish a task alone in 24 days while Andres can do the same task in 18 days. If they work together, how long can they finish the task?
Mark makes of the work per day. It is his rate of work.
Andres makes of the work per day. It is his rate of work.
Working together, they make = = of the work per day.
Hence, it will take = days for them to complete the job working together.
----------------
It is a typical joint work problem.