Question 1080759:  16 workers complete their work in 38 days. In how many days will it take if 5 of the workers increase their work load by 60%?  
 Answer by Theo(13342)      (Show Source): 
You can  put this solution on YOUR website! p*r*t = q
 
 
p = numnber of people 
r = rate that each person works 
t = time 
q = quantity of work produced.
 
 
in your problem, you start with 16 * r * 38 = 1
 
 
p = 16 
r = rate that each person works per day 
t = 38 days 
q = 1 job
 
 
solve for r in this equation to get r = 1/(16 * 38) = 1/608
 
 
each worker completes 1/608 of the job per day.
 
 
16 * 1/608 * 38 = 1 job completed.
 
 
5 of the workers increases their workload by 60%
 
 
1.6 * 1/608 = 1.6/608
 
 
now you have 11 of the workers completing 1/608 of the job per day and you have 5 of the workers completing 1.6/608 of the job per day.
 
 
you want to solve for time.
 
 
when they work together, the worker's rates are additive.
 
 
p * r * t = q becomes:
 
 
(11 * 1/608) + 5 * (1.6/608) * t = 1
 
 
solve for t to get t = 1 / (11 * 1/608) + 5 * 1.6/608) = 32
 
 
the job will be completed in 32 days
 
 
the 5 workers will complete 5 * 1.6/608 * 32 = .4210526316 of the job in 32 days.
 
 
the 11 workers will comlete 11 * 1/608 * 32 = .5789473684 of the job in 32 days.
 
 
combine their efforts and the whole job is completed in 32 days.,
 
 
 
  | 
 
  
 
 |   
 
 |