SOLUTION: It takes 24 days for 8 workers to complete painting a building, how many days will it take 18 workers

Algebra ->  Rate-of-work-word-problems -> SOLUTION: It takes 24 days for 8 workers to complete painting a building, how many days will it take 18 workers      Log On


   



Question 1068638: It takes 24 days for 8 workers to complete painting a building, how many days will it take 18 workers
Answer by josgarithmetic(39618) About Me  (Show Source):
You can put this solution on YOUR website!
8%2Ar%2A24=18%2Ar%2Ax

x=%288%2A24%29%2F18

x=%288%2A4%2A6%29%2F%286%2A3%29

x=32%2F3

x=10%262%2F3
To the nearest whole day, 11 days.