SOLUTION: A crew of ten workers was hired to complete a job in 8 days. After working for two days, there was a new request to complete this job in two days. How many more workers need to be
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A crew of ten workers was hired to complete a job in 8 days. After working for two days, there was a new request to complete this job in two days. How many more workers need to be
Log On
Question 1067620: A crew of ten workers was hired to complete a job in 8 days. After working for two days, there was a new request to complete this job in two days. How many more workers need to be hired to finish this job in 2 days? Found 2 solutions by josmiceli, MathTherapy:Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! I'm assuming that the 10 workers, working at
their normal rate would finish the job in exactly
8 days.
----------------------
The rate of working for 1 worker is:
[ 1/10 of the job ] / [ 8 days ] = [ 1 job ] / [ 80 days ]
This is also [ 1/80 of the job ] / [ 1 day ]
In 2 days, the fraction of the job that gets done is:
The leaves of the job left
-----------------------------------
Now the rate has to be jobs/days
Let = the number of additional workers needed to
finish the job in 2 days
-----------------------------------
Multiply both sides by
-------------------------------------
29 additional workers need to be added
-------------------------------------
check answer: there is a total of workers to
do 39/40 of the job in days
-------------------------------
Each worker will do of the job in days
That is of the job in 1 day
This agrees with my original calculation
-------------------------------
Definitely try to get another opinion on this!
You can put this solution on YOUR website!
A crew of ten workers was hired to complete a job in 8 days. After working for two days, there was a new request to complete this job in two days. How many more workers need to be hired to finish this job in 2 days?
Fraction of job done by 10 workers in 2 days:
Fraction of job remaining after 10 workers worked 2 days:
Now, of job remains to be done in 2 days, by 10 + A, with A being the additional workers
This will take: , or a total of 30 (10 + 20) workers to complete the job in 2 days.