It took two people to complete carpeting in 10 days. How many more carpenters need to be hired to complete the same job in 4 days?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~
1. "It took two people to complete carpeting in 10 days" ---> it means that the entire job is 2*10 = 20 man-days.
2. To complete it in 4 days,
= 5 workers are needed.
3. Since you just have two workers ready, you need 5-2 = 3 additional carpenters.
Answer. 3 additional carpenters are needed.