SOLUTION: It took two people to complete carpeting in 10 days. How many more carpenters need to be hired to complete the same job in 4 days?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: It took two people to complete carpeting in 10 days. How many more carpenters need to be hired to complete the same job in 4 days?      Log On


   



Question 1066910: It took two people to complete carpeting in 10 days. How many more carpenters need to be hired to complete the same job in 4 days?
Answer by ikleyn(52776) About Me  (Show Source):
You can put this solution on YOUR website!
.
It took two people to complete carpeting in 10 days. How many more carpenters need to be hired to complete the same job in 4 days?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~

1.  "It took two people to complete carpeting in 10 days"  --->  it means that the entire job is 2*10 = 20 man-days.


2.  To complete it in 4 days, 20%2F4 = 5 workers are needed.


3.  Since you just have two workers ready, you need 5-2 = 3 additional carpenters.


Answer.  3 additional carpenters are needed.