SOLUTION: Out of the work man x and y,x is twice as good as y to perform the work assigned to them.If x can finish the assigned work in 40 days less than y,then in how many days they togethe

Algebra ->  Customizable Word Problem Solvers  -> Travel -> SOLUTION: Out of the work man x and y,x is twice as good as y to perform the work assigned to them.If x can finish the assigned work in 40 days less than y,then in how many days they togethe      Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 1065767: Out of the work man x and y,x is twice as good as y to perform the work assigned to them.If x can finish the assigned work in 40 days less than y,then in how many days they together can finish the work if they work together?
Answer by Theo(13342) About Me  (Show Source):
You can put this solution on YOUR website!
x can finish the work in 40 days less than y.
x works twice as fast as y, if i understood you correctly.

if we let z = the rate of y, then 2z = the rate of x.

rate * time = quantity of work produced.

quantity of work produced = 1 job.

if we let q = the time it takes y to finish the work, then q - 40 is the time it takes x to finish the work.

when y works, the formula becomes z * q = 1

when x works, the formula becomes 2z * (q-40) = 1

if we solve both of these formulas for z, we get:

z = 1/q and z = 1/(2 * (q-40))

simplify to get z = 1/q and z = 1/(2q-80)

this means that 1/q = 1/(2q-80)

cross multiply to get 2q-80 = q

subtract q from both sides of this equaiton to get q-80 = 0

solve for q to get q = 80

when y works, you get zq = 1 which becomes 80z = 1 which becomes z = 1/80.

when x works, you get 2z(q-40) = 1 which becomes 2z(80-40) = 1 which becomes 2z*40 = 1 which becomes 2z = 1/40.

remember now, that the rate of y is z and the rate of x is 2z.

the rate of x is 1/80 of the job in 1 day.

the rate of y is 1/40 of the job in 1 day.

when they work together, their rates are additive, so you get:

(1/80 + 1/40) * q = 1

q in this case is the time it takes when they are working together.

simplify to get 3/80 * q = 1

solve for q to get q = 80/3 = 26 and 2/3 days.

your answer should be that they take 26 and 2/3 days to complete the job when they work together. if i understood your problem correctly.

when x works alone, he takes 40 days to complete the job.
when y works alone, he takes 80 days to complete the job.

x takes 40 days less than y to complete the job, so that part checks out.

the rate of x is 1/40 of the job in one day while the rate of y is 1/80 of the job in 1 day, so the rate of x is twice the rate of y, so that part checks out as well.

i believe that 26 and 2/3 days to complete the job when they work together is the solution you are looking for.