SOLUTION: Machine A can do a certain job in 8 hours. machine B can do the same job in 10 hours. machine C can do the same job in 12 hours. all three machines start the job at 9.00 am, machin

Algebra ->  Test -> SOLUTION: Machine A can do a certain job in 8 hours. machine B can do the same job in 10 hours. machine C can do the same job in 12 hours. all three machines start the job at 9.00 am, machin      Log On


   



Question 1064251: Machine A can do a certain job in 8 hours. machine B can do the same job in 10 hours. machine C can do the same job in 12 hours. all three machines start the job at 9.00 am, machine B breaks down at 11.00am and the other two machines finish the job. approximately at what time would the job be completed?
(please explain the method)

Answer by Boreal(15235) About Me  (Show Source):
You can put this solution on YOUR website!
in one hour
A does 1/8, B does 1/10, C does 1/12
x is the number of total hours worked.
B worked 2 hours
2/8+2/10+2/12=30/120+24/120+20/120=74/120 of the job done by all three.
The other two account for 46/120; that comes from the fact that if 74/120 was done by all 3, the remaining 46/120 (74+46=120) were done by the two remaining machines.
x/8+x/12=46/120
15x/120+10x/120=46/120
15x+10x=46
25x=46
x=1.84 hours or 12:50.24 ANSWER
check
A worked 3.84 hours, B 2 hours and C 3.84 hours
3.84/8+2/10+3.84/12=
common denominator=120
57.6+24+38.4 is the numerator, which adds to 120.