SOLUTION: A construction company needs to remove 30 tons of dirt from a construction site. They can remove 3/5 tons of dirt each hour. How long will it take to remove the dirt?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A construction company needs to remove 30 tons of dirt from a construction site. They can remove 3/5 tons of dirt each hour. How long will it take to remove the dirt?
Log On
Question 1054672: A construction company needs to remove 30 tons of dirt from a construction site. They can remove 3/5 tons of dirt each hour. How long will it take to remove the dirt? Answer by Alan3354(69443) (Show Source):