Question 1054426
:
A carpenter van build a house in 8 days. How much would he have done in 5 days
Answer by
jorel555(1290)
(
Show Source
):
You can
put this solution on YOUR website!
1/8 x 5=5/8ths of a house done in 5 days. ☺☺☺☺