SOLUTION: 7 men take5 weeks to complete a job. Working at the same rate, how long do 10 men take to complete the same job

Algebra ->  Conjunction -> SOLUTION: 7 men take5 weeks to complete a job. Working at the same rate, how long do 10 men take to complete the same job       Log On


   



Question 1046942: 7 men take5 weeks to complete a job. Working at the same rate, how long do 10 men take to complete the same job
Answer by ikleyn(52787) About Me  (Show Source):
You can put this solution on YOUR website!
.
%287%2A5%29%2F10 = 3.5 weeks.