SOLUTION: 7 men take5 weeks to complete a job. Working at the same rate, how long do 10 men take to complete the same job
Algebra ->
Conjunction
-> SOLUTION: 7 men take5 weeks to complete a job. Working at the same rate, how long do 10 men take to complete the same job
Log On
Question 1046942: 7 men take5 weeks to complete a job. Working at the same rate, how long do 10 men take to complete the same job Answer by ikleyn(52787) (Show Source):