Question 1036966
:
If it takes a crew 9 days to do 80% of the job, how many more days will it take to finish the job 100%
Answer by
josmiceli(19441)
(
Show Source
):
You can
put this solution on YOUR website!
Their rate of working is:
jobs / days
Divide top and bottom by
jobs / days
The job can be finished in 2.25 days