Question 1034699: A and B can paint a wall in 3 days. A can do it alone in 5 days. how many days would it take for B alone? Answer by ikleyn(52818) (Show Source):
You can put this solution on YOUR website! .
A and B can paint a wall in 3 days. A can do it alone in 5 days. how many days would it take for B alone?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
The rate of A+B is of the job-per-day.
The rate of A is of the job-per-day.
Hence, the rate of B is = = of the job-per-day.
Answer. It will take = for B to complete the job working alone.