Question 1033952: if 3 workers can finish painting a house in 2 days, how many days will it take 6 workers to paint 5 of those (identical) house if they work at the same speed?
Found 3 solutions by josgarithmetic, josmiceli, ikleyn:
Answer by josgarithmetic(39617) About Me  (Show Source):
You can put this solution on YOUR website!
RT=W relates work rate, time, and amount of work. The basic situation needs an adjustment as nRT=W and the rate for n workers each acting together at rate R is nR.

3 workers can finish painting a house in 2 days
means 3r%2A2=1. The rate for 1 worker is r. One job to be done is "paint 1 house".


how many days will it take 6 workers to paint 5 of those (identical) house if they work at the same speed?
Let t be the unknown number of day.
6r%2At=5


I stop here and you should use the information developed to solve the problem all the way through.

Answer by josmiceli(19441) About Me  (Show Source):
You can put this solution on YOUR website!
3 workers can finish painting a house in 2 days
1/3 that number of workers will take 3 times as long, so
1 worker can finish painting a house in 6 days
-------------------------------------
6 workers will take 1/6 as long to paint a house, so
6 workers can finish painting a house in 1 day
---------------------------------------
5 houses will take 5 times as long, so
6 workers can finish painting 5 houses in 5 days

Answer by ikleyn(52786) About Me  (Show Source):
You can put this solution on YOUR website!
.
if 3 workers can finish painting a house in 2 days, how many days will it take 6 workers to paint 5 of those (identical) house if they work at the same speed?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Make an equation by equating job rates in both cases:


1%2F%283%2A2%29 = 5%2F%286%2Ax%29.


The left side is job rate of 3 workers painting 1 houses in 2 days.
The right side is job rate of 6 workers painting 5 houses in x days.

Now solve this proportion for x. For it, cross-multiply:

3*2*5 = 6*x

x = 3%2A2%2A5%2F6 = 5.

Answer.  5 days.