SOLUTION: if 12 men build 700 houses in 9 days, how long will it take 18 men to build the same 700 houses?
Algebra
->
Rate-of-work-word-problems
-> SOLUTION: if 12 men build 700 houses in 9 days, how long will it take 18 men to build the same 700 houses?
Log On
Word Problems: Rate of work, PAINTING, Pool Filling
Word
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Rate-of-work-word-problems
Question 1029480
:
if 12 men build 700 houses in 9 days, how long will it take 18 men to build the same 700 houses?
Answer by
Natolino1983(23)
(
Show Source
):
You can
put this solution on YOUR website!
Let's say that w is the individual velocity, and d the amount of days when 18 men are used.
w= 700/(12×9) = 175/27 (houses/day).
So d×w×18 =700, then d= 700/(w×18) =108/18 =6 days.