Question 1021596
:
if it took 8 builders 25 days to build a house how long would it take 10 builders to do the same job.
Answer by
robertb(5830)
(
Show Source
):
You can
put this solution on YOUR website!
It would require 8*25 = 200 man-days to build the house.
==>
<==>
==> x = 20 days.