SOLUTION: 18men can build 6 boats in 35days .how many men working at twice the the same rate,can build 4similar boats in 14 days
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: 18men can build 6 boats in 35days .how many men working at twice the the same rate,can build 4similar boats in 14 days
Log On
You can put this solution on YOUR website! How you mean the rate is uncertain. The assumption made will be r is the one-man rate and that twice
the number of men would be used to make the group rate double.
The first part gives ------the one-man rate.
Using 2 men would give as the TWO-man rate.
Question would be how many of two-men build 4 ships in 14 days?
n, how many of two-men,
This should be .
The other interpretation from the beginning may be EACH man will work at DOUBLE his typical rate
so the one-man rate could be , and then would really be FIFTEEN men.