SOLUTION: Man finish the paint of wall in 15 days how many man are requried to done the work in one and the half days

Algebra ->  Rate-of-work-word-problems -> SOLUTION: Man finish the paint of wall in 15 days how many man are requried to done the work in one and the half days       Log On


   



Question 1012528: Man finish the paint of wall in 15 days how many man are requried to done the work in one and the half days

Answer by fractalier(6550) About Me  (Show Source):
You can put this solution on YOUR website!
The wall takes one man 15 days. That means the task takes 15 man-days.
If you want it done in 1.5 days, divide 15 by 1.5 and get
10 men.