Question 1011891
:
15 men complete a job in 10 days, 8 men finish same job ? how many days
Answer by
josgarithmetic(39617)
(
Show Source
):
You can
put this solution on YOUR website!
r, rate for 1 man
t, unknown days,
This is for 1 job.
RT=J to relate rate, time, job