Question 1006778: A farmer employee 12 men to harvest his crops they took 9days if he had employ 16men how many days it would take them ? Found 2 solutions by josgarithmetic, addingup:Answer by josgarithmetic(39620) (Show Source):
You can put this solution on YOUR website! Convert this to man-days. If it takes 12 men 9 days, then:
(12 men) × (9 days) = 108 man-days
That is, the entire job requires 108 man-days. So if we had 16 men, then:
108/16= 6.75 days