SOLUTION: if 8 men working 9 h a day can reap a field in 24 day in how many day will 12 men reap the field working 6 h a day

Algebra ->  Test -> SOLUTION: if 8 men working 9 h a day can reap a field in 24 day in how many day will 12 men reap the field working 6 h a day      Log On


   



Question 1000562: if 8 men working 9 h a day can reap a field in 24 day in how many day will 12 men reap the field working 6 h a day
Answer by josgarithmetic(39625) About Me  (Show Source):
You can put this solution on YOUR website!
RT=J basic uniform rate rule relating rate, time, and amount of work or job.

Let r be the rate for ONE MAN, in the unit FIELDS per DAY. You would express and mean the rate as 1 field per number of days.
Let d be the unknown number of days for the question.

The description turned into equations:

The amount of hours per day ratio was included in each equation for the two separate parts of the description. The variable, d, is for TIME in DAYS. The question is also about time in DAYS.

To condense some of the notation about the units to have more easily-read system,
system%288r%2A9%2A24=1%2C12r%2A6d=1%29
Solve for d.