SOLUTION: A company contracts to paint 3 houses. Mr.Orange can paint a house in 6 days while Mr.Grey would take 8 days and Mr.Red 12 days. After 8 days Mr.Orange goes on vacation and Mr.Grey

Algebra ->  Customizable Word Problem Solvers  -> Mixtures -> SOLUTION: A company contracts to paint 3 houses. Mr.Orange can paint a house in 6 days while Mr.Grey would take 8 days and Mr.Red 12 days. After 8 days Mr.Orange goes on vacation and Mr.Grey      Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 729572: A company contracts to paint 3 houses. Mr.Orange can paint a house in 6 days while Mr.Grey would take 8 days and Mr.Red 12 days. After 8 days Mr.Orange goes on vacation and Mr.Grey begins to work for a period of 6 days. How many days will it take Mr.Red to complete the contract?
Found 2 solutions by lynnlo, ikleyn:
Answer by lynnlo(4176) About Me  (Show Source):
Answer by ikleyn(53418) About Me  (Show Source):
You can put this solution on YOUR website!
.
A company contracts to paint 3 houses. Mr.Orange can paint a house in 6 days while Mr.Grey would take 8 days
and Mr.Red 12 days. After 8 days Mr.Orange goes on vacation and Mr.Grey begins to work for a period of 6 days.
How many days will it take Mr.Red to complete the contract?
~~~~~~~~~~~~~~~~~~~~~~~

The whole job is to paint 3 houses.


Mr. Orange' rate of work is  1%2F6  of the house per day.

Working 8 days, Mr Orange painted  8%2F6 = 4%2F3  houses, and  3 - 4%2F3 = 5%2F3 houses remained
to paint.



Mr. Gray' rate of work is  1%2F8  of the house per day.

Working 6 days, Mr. Gray painted  6%2F8 = 3%2F4  of a house, and  

   5%2F3 - 3%2F4 = 20%2F12 - 9%2F12 = 11%2F12 of a  house remained to paint.




Mr. Red' rate of work is  1%2F12  of the house per day.

Hence, he needs 

    %28%2811%2F12%29%29%2F%28%281%2F12%29%29 = 11 days to complete the contract.


ANSWER.  Mr. Red needs 11 days to complete the job.

Solved.