Question 690740: Two harvesters take one hour to harvest a field. One of these harvesters takes 1.5 hrs. How long does it take the second harvester to do the field alone? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! The rate of harvesting for the 2 harvesters working together is ( 1 field ) / ( 1 hr )
The rate of harvesting for the 1st harvester is ( 1 field ( / ( 1.5 hrs )
Let = the time in hrs for the 2nd harvester working alone
The 2nd harvester's rate would be ( 1 field ) / ( t hrs )
---------------------
Add their rates to get their rate working together
Multiply both sides by
It takes 3 hrs for the 2nd harvester working alone
to harvest the field