SOLUTION: assume it took around 40 carpenters to build a shed in 20 days. Assuming the carpenters work at the same rate, how long would it take six carpenters to build a shed?
Algebra ->
Customizable Word Problem Solvers
-> Misc
-> SOLUTION: assume it took around 40 carpenters to build a shed in 20 days. Assuming the carpenters work at the same rate, how long would it take six carpenters to build a shed?
Log On
Question 157218: assume it took around 40 carpenters to build a shed in 20 days. Assuming the carpenters work at the same rate, how long would it take six carpenters to build a shed? Answer by checkley77(12844) (Show Source):
You can put this solution on YOUR website! 20*40=800 work days to build the shed.
800/6=133.33 days to build the shed using inly 6 carpenters.