SOLUTION: Six men working at the same rate can weed a farm in 16 days. After working for 4 days, 2 more men were hired. How long did they take to weed the farm?
Algebra ->
Customizable Word Problem Solvers
-> Misc
-> SOLUTION: Six men working at the same rate can weed a farm in 16 days. After working for 4 days, 2 more men were hired. How long did they take to weed the farm?
Log On
Question 1156875: Six men working at the same rate can weed a farm in 16 days. After working for 4 days, 2 more men were hired. How long did they take to weed the farm? Found 3 solutions by mananth, josgarithmetic, ikleyn:Answer by mananth(16949) (Show Source):
You can put this solution on YOUR website! Six men working at the same rate can weed a farm in 16 days. After working for 4 days, 2 more men were hired. How long did they take to weed the farm?
6 men ----16 days
1 man-----x days
1 man does 1/96 of the job in 1 day
6 men will do 6/96 =1/16 of the job in 1 day
they work for 4 days so they complete 4*1/16 of the job = 1/4 of the job
Balance job = 1-(1/4) = 3/4 of the job
8 men will complete 8*1/96 of the job in 1 day= 1/12 of the job
1/12 of the job in 1 day
3/4 of the job in y days
y = (3/4)/(1/12)
y = Balance job in 9 days
9+4 =13 days
The job will be completed in 13 days instead of 16 days
You can put this solution on YOUR website! -------------------------------------------
Six men working at the same rate can weed a farm in 16 days.
--------------------------------------------
r, the rate for one man
For one job of "weed a farm", and 6 men doing this job, .
Or, .
----------------------------------------------------------------
After working for 4 days, 2 more men were hired. How long did they take to weed the farm?
---------------------------------------------------------------
"They" meaning all 6+2=8 men together to finish the job.
-
--------------------- nine more days after hiring the two more men
You can put this solution on YOUR website! .
Six men working at the same rate can weed a farm in 16 days. After working for 4 days, 2 more men were hired.
How long did they take to weed the farm?
~~~~~~~~~~~~~~~~~~~~~~~~~~~
I will show another way to solve, using different reasoning than that in the post by @mananth.
Its advantage is that NEITHER fractions NOR equations are used.
The total job is 6 men * 16 days = 96 man-days.
6 men used 6*4 = 24 man-days; 96 - 24 = 72 man-days work remained.
Now 6 + 2 = 8 men work. They need 72/8 = 9 days to complete the remaining job.
So, 8 men will complete the rest of the job in 9 days.
In all, the whole job will be complete in 4 + 9 = 13 days.
Solved completely, using mental reasoning instead equations and fractions.