SOLUTION: in checking records finds that crew A can pave a contract length of highway in 8 hours. Crew B can do the same job in 10 hours. how long would it take if they worked together?
Algebra ->
Customizable Word Problem Solvers
-> Evaluation
-> SOLUTION: in checking records finds that crew A can pave a contract length of highway in 8 hours. Crew B can do the same job in 10 hours. how long would it take if they worked together?
Log On
Question 618539: in checking records finds that crew A can pave a contract length of highway in 8 hours. Crew B can do the same job in 10 hours. how long would it take if they worked together? Answer by scott8148(6628) (Show Source):