SOLUTION: in checking records finds that crew A can pave a contract length of highway in 8 hours. Crew B can do the same job in 10 hours. how long would it take if they worked together?

Algebra ->  Customizable Word Problem Solvers  -> Evaluation -> SOLUTION: in checking records finds that crew A can pave a contract length of highway in 8 hours. Crew B can do the same job in 10 hours. how long would it take if they worked together?       Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 618539: in checking records finds that crew A can pave a contract length of highway in 8 hours. Crew B can do the same job in 10 hours. how long would it take if they worked together?
Answer by scott8148(6628) About Me  (Show Source):
You can put this solution on YOUR website!
(x / 8) + (x / 10) = 1