Question 1028224: 40 men can complete a work in 40 days. They started the work together But at the end of each day 10th day, 5 men left the job, the work would have completed in
a)56 2/3 days
b)53 1/3 days
c)52 days
d)50 days

Answer by fractalier(6550) About Me  (Show Source):
You can put this solution on YOUR website!
Here the job takes 40*40 = 1600 man-days.
After the 10th day, 1/4 of the job was done. 3/4 of the job to go...that would be 1200 man-days.
Five men leaving means there are 35 to finish...
The number of days to finish is
1200/35 = 34 2/7 days
And even if you add the original 10 days, you don't get one of the choices.
Please repost with the correct problem.